2025-2026 Street Project underway!
Milling streets has started and this is the schedule as we know it now:
3/9: Milling on Ben Street and Mike Lounge Drive
3/10: Start repaving Ben Street
3/10 – 3/12: Milling on Fay Street from Mike Lounge Drive to South 14th Street.
3/12 – 3/13: Milling on South 14th Street from Fay Street to Rose Avenue.
To follow: Martin Avenue from 14th Street to 8th Street.
At the high school, the intersection of Mike Lounge Drive and Mildred Street will be left open for access to the school parking lot from the west.
Paving the streets will follow the path of the milling process.
This project is estimated to take 2-3 weeks.
Updates will be provided as we receive them.